Campbell Veterans Memorial Hits a Snag

Completion of Phase 1 of the construction is tentatively scheduled for May 28.

Activity at the at Campbell City Hall has stalled but not stopped altogether.

"We ran into a design problem," says Jim Free, Campbell Veterans Memorial Foundation past president.

After excavation began at the project site, utility lines running underneath a portion of the future memorial were found.

"It's a slight design change," says Campbell Veterans Memorial Foundation President Dan Furtado

The project will have to move the planned flagpoles over about 24 inches, Furtado says.

Once the construction begins again, the foundation says that completion of Phase 1 is tentatively scheduled for May 28. With that, the project will be about a third of the way completed.

Mike katz April 04, 2012 at 12:39 PM
These guys are so dedicated to this project....if you can, please support them!! gotta love our vets!!

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something